FAT (factory acceptance test)

Testing equipment at the supplier's works before shipment to confirm it is built and performs as specified, witnessed or reviewed by the buyer.

A FAT is carried out before equipment leaves the supplier. Typical checks include dimensions and build against approved drawings, materials and documentation, pressure tests, electrical and control panel checks, and running tests where the test bench allows. For control systems it includes simulated I/O, alarms, interlocks and PLC logic.

The value is finding problems where they are cheapest to fix. A wiring fault or missing tag found at the supplier costs far less than one discovered on a live site with production waiting.

Agree the FAT procedure, acceptance criteria and witness arrangements in the purchase specification, not after delivery. Record results and punch items, and carry open items forward to the SAT so nothing is lost between the two.

Next step

Need this applied to your plant?

We turn definitions into specifications, then into equipment that meets them.

Start typing to search