The SAT follows installation and commissioning. It proves that the complete system works on site: equipment runs, controls and sequencing behave as designed, alarms and interlocks trip correctly, instruments read correctly and performance meets the agreed criteria. For compressed air that usually includes delivered pressure, pressure dew point, air quality checks against the specified class and SCADA signals.
It is the formal point where the owner confirms the system is fit to accept. Any open items go on a punch list with owners and dates.
A good SAT tests against written criteria agreed in advance, ideally carried forward from the FAT. Keep the signed records with the as-built drawings and manuals; they become the baseline for future maintenance and audits.