Why audit before you spend
Most compressed air decisions are made without data. A compressor is replaced because it is old. A larger one is bought because pressure is low. A dryer is added because water appeared after rain. Some of these decisions are right. Many treat a symptom and leave the cause in place.
An air audit replaces opinion with measurement. It shows what your system consumes, what it delivers, where the losses are and which fixes are worth paying for. It also gives you a baseline, which is the only fair way to prove later that a change saved anything at all.
What we measure
We measure the system across a representative production period, not a snapshot. The exact set depends on the site, but a typical audit covers the following.
Typical audit measurements
- Electrical power of each compressor, logged continuously
- Loaded, unloaded and stopped time for each machine
- Pressure at the compressor discharge, after treatment and at key points of use
- Delivered flow, from existing meters or temporary measurement
- Pressure dew point after the dryers
- Pressure drop across dryers and filters
- Compressor room temperature and ventilation
- Leaks, located and tagged by ultrasonic survey
- Demand when production is stopped
- How air is used: open blowing, cooling and other inappropriate or artificial demand
From these we calculate specific energy in kWh/m³, the efficiency figure for the whole hall, along with the unloaded power cost, the pressure profile and the leak rate.
Our method: Measure, Prioritise, Implement, Verify
1. Measure. We install loggers and instruments, run the leak survey, and collect production data so consumption can be normalised. We also inventory every compressor, dryer, filter, receiver and drain, and note its condition.
2. Prioritise. We analyse the data and build a list of actions. Each one is ranked by expected energy saving, investment, payback and practicality. Some are free, such as changing a setpoint or a compressor’s role. Some need modest spend, such as leak repair and zero-loss drains. Some need capital, such as a VSD trim compressor or re-piping.
3. Implement. You decide what to do. We can carry out the work, or your team can. If we do it, design and engineering and installation follow the same documented process as any other project.
4. Verify. After implementation, we measure again, under comparable conditions, using the plan agreed before the work began.
A saving you cannot measure is a promise. A saving you have measured is a result.
What you receive
The sample deliverable on this page shows the format. Every audit produces four documents.
- Baseline report. How the system performs today: consumption, specific energy, load profiles, pressure profile, dew point, leakage and the condition of each item of equipment.
- Ranked action list. Each recommended action with its expected saving, the work involved and its priority.
- Investment and payback assumptions. The cost basis, tariff, operating hours and other assumptions behind each payback figure, set out so your finance team can check them.
- Verification plan. What will be measured after implementation, for how long, how results will be normalised for production, and how the saving will be calculated.
How savings are calculated
We calculate savings one way, and we agree the inputs before any work starts.
Savings are project-specific. We measure them against a baseline and verify them after implementation; we don’t promise a blanket percentage.
ISO 11011: the system view
Who an audit is for
An audit is worth doing when the electricity bill is rising, when pressure or moisture problems keep returning, before you buy a new compressor, or before a renovation. It is the first step of our energy optimisation and plant renovation work, and often the reason a plant adds AirSight monitoring afterwards.
Want a quick estimate first? Try the compressed air cost calculator or the leak cost calculator. For background, read what a compressed air audit involves.